Vernon Campus Construction Pictures
|
| August 8-24 - September 2 |
![]() ![]() ![]() ![]() |
|
September 12-16
|
![]() ![]() ![]() |
|
September 19-24 |
![]() ![]() ![]() ![]() |
|
Schedule: As of 9/14/06, the footings have been excavated and rebar is being installed. Footings are scheduled to be poured week of 9/18/06. Site work consists of grading, irrigation sleeving and site lighting. Off-site and on-site curb, gutter and sidewalks to follow in the weeks to come. The project is expected to be complete in July of 2007. September 25 - October 1
|
![]() ![]() ![]() ![]() |
October 2 - 9 |
| October 10 - 15 Pouring concrete for the foundation |
![]() ![]() ![]() |
October 16-21 Working on the new sidewalks around the property |
October 22-28 Working the foundations & Preparing the Parking Lot |
![]() ![]() ![]() ![]() |
![]() ![]() ![]() ![]() |
|
Click on the links below for More Pictures |