Vernon Campus Construction Pictures
September - October 2006
Return to Vernon Home Page

August 8-24 - September 2

September 12-16

September 19-24


Schedule: As of 9/14/06, the footings have been excavated and rebar is being installed. Footings are scheduled to be poured week of 9/18/06. Site work consists of grading, irrigation sleeving and site lighting. Off-site and on-site curb, gutter and sidewalks to follow in the weeks to come. The project is expected to be complete in July of 2007.

September  25 - October 1

October 2 - 9

October 10 - 15
Pouring concrete for the foundation
October 16-21
Working on the new sidewalks around the property

October 22-28
Working the foundations & Preparing the Parking Lot

 
 