Vernon Campus Construction Pictures
|
| Nov 1-5 (Parking Lot Gets Prepared for Paving) |
![]() ![]() ![]() ![]() |
|
Schedule: As of 11/01/06, the stem walls have been poured. Underslab utilities are being installed. The first of four slab pours is scheduled for 11/3/06. Structural steel is scheduled for erection by mid-November. On-site curbs are complete and the site is scheduled to pave 11/6/06. Off-site curb, gutter and sidewalk is nearly complete. The project is expected to be completed in July of 2007. |
|
|
![]() ![]() ![]() |
|
November 13-19
|
![]() ![]() ![]() ![]() |
November 21-23 (Preparing the Foundation) |
November 27-28 The Foundation Gets Poured |
![]() ![]() ![]() ![]() |
![]() ![]() ![]() ![]() |
|
![]() ![]() ![]() ![]() |
![]() ![]() ![]() ![]() |