Vernon Campus Construction Pictures
|
Week of March 2, 2007 |
![]() ![]() ![]() ![]() |
|
Week of March 16, 2007 |
![]() ![]() ![]() ![]() |
Week of March 23, 2007 |
![]() ![]() ![]() ![]() |
Week of March 28, 2007 |
![]() ![]() ![]() ![]() |
![]() ![]() ![]() ![]() |
|
Schedule: As of 2/21/07, exterior sheathing is complete, single ply roofing complete, windows are being installed, and lath is to start before the end of February. Interior mechanical, electrical and plumbing rough-in is in progress along with metal stud framing on the first floor nearing completion and metal stud framing on the second floor in progress. On-site curbs are complete,the parking lot and drive aisles were paved 11/6/06 and all off site work is complete as well.
|