Vernon Campus Construction Pictures
December 2006
Return to Vernon Home Page


December 1-8 The Structure Continues to Goes Up
Shchedule: As of 11/30/06, the majority of the slab on grade has been placed. Structural steel erection started 11/29/06. On-site curbs are complete and the parking lot and drive aisles were paved 11/6/06. The project is expected to be completed in July of 2007.


Week of December 1
2-17
Schedule:As of 12/15/06, the interior slab on grade has been poured and structural steel is nearing completion. Wood and metal stud framing are to start early January. On-site curbs are complete and the parking lot and drive aisles were paved 11/6/06. The project is expected to be completed in July of 2007.

Week of December 18-24

Week of December 29

July-August | September - October | November | December | January 07
| February 07 | March 07 | April 07